What changes were made in the October 14, 2014 amendments and when do they go into effect?
A
State Construction Notices Directory will be created for posting
Owner’s Notice of Commencement, Subcontractor’s Notice of Furnishing,
Owner’s Notice of Nonpayment, and Owner’s Notice of Completion. The
system applies to projects costing at least $1,500,000, referred to as
“searchable projects”. Participation in the system is optional in the
discretion of the owner. An owner of a searchable project who wants to
participate must file with the Directory and post at the job site a
notice of commencement prior to commencement of labor, work, and
furnishing of materials, providing certain categories of information
about the project. If a searchable project owner makes the required
filing and posting, a subcontractor who fails to file a notice of
furnishing within 45 days after commencing work loses all rights to file
a mechanics’ lien with respect to the project.
The State Construction Notices Directory will become operational on December 31, 2016.
What changes were made in the July 9, 2014 amendments and when did they go into effect?
To counter Commerce Bank/Harrisburg N.A. v. Kessler,
46 A.3d 724 (Pa. Super. 2012), the construction loan priority provision
was clarified to provide that open-ended mortgages have priority over
mechanics’ liens where at least 60 percent of the proceeds are intended
to pay or are used to pay all or part of the costs of construction. A
definition was also added for “costs of construction” that includes most
of the expenses (soft as well as hard) that are incurred in a
construction project.
Subcontractors no longer have a right to
lien residential properties consisting of 1 or 2 dwelling units in a
single building or townhouse where the owner or tenant has paid the full
contract price to the contractor.
The changes in the July 9, 2014
amendments apply to liens perfected on or after July 9, 2014, even if
the visible commencement of construction preceded that date.
What changes were made in the August 11, 2009 amendments and when did they go into effect?
The
term “residential building” was replaced with “residential property”
which is defined as “property on which there is or will be constructed a
residential building not more than three stories in height, not
including any basement level regardless of whether any portion of that
basement is at grade level, or which is zoned or otherwise approved for
residential development on which there is or will be constructed a
residential building not more than three stories in height, not
including any basement level, regardless of whether any portion of the
basement is at grade level, planned residential development or
agricultural use, or for which a residential subdivision or land
development plan has or planned residential development plan has
received preliminary, tentative or final approval on which there is or
will be constructed a residential building not more than three stories
in height, not including any basement level, regardless of whether any
portion of that basement is at grade level, pursuant to the act of July
31, 1969 (P.L. 805, No. 247), known as the “Pennsylvania Municipalities
Planning Code.”
Advance waivers of lien for contracts to
construct residential properties are not limited by a monetary cap on
the total contract price.
The changes in the August 11, 2009 amendments went into effect on October 10, 2009.
Carl G. Roberts, Esquire (Contributing Author) - Ballard Spahr LLP
Friday, December 12, 2014
Monday, December 1, 2014
Lien Law Online eLert for 12/1/2014 - Virginia
December 1, 2014
Lien
Law On-line is pleased to announced that the Virginia chapter has been revised
to advise that the notice to the person or entity designated on the building
permit for a one or two family residential dwelling unit must include the
person’s or entity’s license or certificate number issued by the Board of
Contractors and the date such license or certificate was issued and will
expire.
John
S. Morris, III, Esquire (Contributing Author)
Beale, Davidson, Etherington
& Morris, P.C.
www.lienlawonline.com
Wednesday, April 16, 2014
Lien Law Online eLert for 4/16/2014 - Mississippi
April
15, 2014
Please
note that on April 11, 2014, Mississippi enacted a new lien law that extends
lien rights to subcontractors, materials suppliers, and sub-subcontractors and
material suppliers to subcontractors (http://billstatus.ls.state.ms.us/documents/2014/pdf/SB/2600-2699/SB2622SG.pdf). The new law also
has a much shorter "window" within which to file a lien and suit to
enforce a lien. Finally, the new law includes owner defenses and statutory
lien waivers.
A
revised Mississippi chapter will be available soon. We will notify you as soon as the updated
chapter is posted.
David W. Mockbee (Contributing Author)
Tuesday, November 12, 2013
Lien Law Online eLert for 11/4/2013 - Kentucky
21. Two relevant cases:
PBI
Bank, Inc. v. Schnabel Found. Co., No. 2011-CA-001135-MR (Ky. App. Jan.
25, 2013) – equitable tolling applied to allow untimely lien statement to
relate back to a prior lien statement that the county clerk had wrongly refused
to file. **Case
is “to be published” but hasn’t been yet**
Schnabel
Foundation Company (“Schnabel”) provided labor and materials on the Harrods
Creek Overlook Condominiums project in Prospect, Kentucky (the
“Project”). The Project was owned by Premier Land Company
(“Premier”). Premier obtained a mortgage on the property from PBI Bank,
Inc. (“PBI”).
Schnabel’s
last day of work was August 27, 2007. On February 22, 2008, Schnabel’s
counsel mailed a lien statement to the Jefferson County Clerk for
recordation. The clerk refused to file the statement because Schnabel’s
counsel had not signed as the preparer of the statement.
When
Premier defaulted on its mortgage, PBI moved for foreclosure on May 20, 2008
and named Schnabel as a defendant. Nine days later, on May 29, 2008,
Schnabel recorded its Mechanic’s Lien (which included a signature by the
preparer).
Schnabel
and PBI moved for summary judgment on the enforceability of the lien. The
court first examined whether the February 22, 2008 lien statement was
improperly rejected by the Jefferson County Clerk. KRS 382.335(1)
requires that lien statements must include “the name and address of the
individual who prepared the instrument” and must be signed by the individual
who prepared them. The appellate court determined that Schnabel’s
attorney had signed the lien statement and had included a “‘prepared by
statement’ listing [the attorney’s] name and address” but had not signed
separately as the preparer. “KRS 382.335(1) does not require that the
preparer of the statement sign the instrument in a specific form or
location. It only requires that the person who prepared the instrument
execute his signature by ‘affixing a facsimile of his on the instrument.”
Id. at slip op. 4. Therefore, because Schnabel had signed the
first lien statement, the court determined that it had been improperly rejected
by the County Clerk.
The
court then examined whether equitable tolling would allow the untimely second
lien statement to relate back to the improperly rejected first lien statement
(the second lien statement was untimely because it was filed more than six
months after Schnabel’s last day of work, in violation of KRS 376.080).
As Schnabel “could not force the county clerk to perform official duties and
file the [first lien statement],” the Court of Appeals affirmed the application
of equitable tolling and thereby the lower court’s judgment in favor of
Schnabel. Id. at slip op. 5.
Dreamers,
LLC v. Don’s Lumber & Hardware, Inc., No. 2009-CA-000978-MR (Ky. App. Jan.
11, 2013) – examination of notice requirement **Opinion is not to
be published**
The
Dreamers, LLC (“Dreamers”) purchased materials from Don’s Lumber &
Hardware, Inc. (“DLH”) on credit and incorporated those materials into the
construction of a new house in Radcliff, Kentucky. Dreamers sold the
completed house to Appellant Glenda Hoffman.
When
DLH was not paid for its materials, it filed a Mechanic’s Lien against the
house and later sued to foreclose the lien. The case was before the Court
of Appeals on several grounds, including the Appellants’ claim that summary
judgment was improper because DLH had failed to comply with the notice
provisions of KRS 376.010(3) and (4). The Court of Appeals found no merit
in this argument, explaining that the record showed that DLH had given notice
to Hoffman within sixty days of last performing work on the property.
Therefore DLH had complied with the requirements of KRS 376.010(3) and
(4).
S2. Statutory discussion of Kentucky Fairness in
Construction Contracting Act applicable to mechanics liens
A.J. Manion (Contributing Author)
Manion Stigger LLP
Lien Law Online eLert for 11/4/2013 - Mississippi
November
4, 2013
"On
October 10, 2013, the United States Court of Appeals for the Fifth Circuit in
Noatex Corp. v. King Constr. of Houston, LLC, 2013 U.S. App. LEXIS 20656 (5th
Cir., Oct. 10, 2013) held that Mississippi’s Stop Payment Notice statute, Miss.
Code Ann. §85-7-181, is an unconstitutional violation of procedural due
process. Accordingly, since only those who have a direct contractual
relationship with the owner, his agent, or his representative are afforded the
protection of a lien, subcontractors and suppliers to general contractors
currently do not have any type of lien or payment protection rights."
David
Mockbee, Contributing Author
Mockbee
Hall & Drake, P.A.
Wednesday, September 11, 2013
Lien Law Online eLert for 9/10/2013 - Louisiana
September
10, 2013
This
past year the Louisiana legislature enacted a handful of amendments which have
changed the notice requirements and time for enforcement of certain lien
claimants under the Private Works Acts. The most important change is that a
lien claimant is now required to file suit within one year of the recordation
of its Statement of Claim or Privilege, whereas before the deadline to file
suit to enforce the claim was one year after the expiration of the time to file
a lien. In addition, lessors of movables are now required to provide the
owner and contractor with a signed copy of the lease agreement identifying the
terms of rental and of payment. Lastly, recent jurisprudence which
addressed the requirement of itemization in a Statement of Claim or Privilege
prompted legislative changes to clarify that unpaid invoices are required to be
attached to a Statement of Claim or Privilege only if the lien specifically
states that such invoices are attached.
H.
Bruce Shreves (Contributing Author)
Peter S. Thriffiley, Jr. (Contributing Author)
Simon Peragine Smith & Redfearn LLP
Monday, September 9, 2013
Lien Law Online eLert for 9/4/2013 - Virginia
September 4, 2013
VIRGINIA LIEN LAW CHANGE Please note
that there has been a change to Virginia’s lien law. Lien claimants that provided labor for the
construction of an improvement must hold a valid license or certificate from
the Virginia Board of Contractors in the proper class of license for the value
of the work performed in order to have a valid lien. The claimant must have the license when the
work is performed. It will not be
sufficient to obtain a license after the work is performed, but before the lien
is filed. The forms for mechanics’ liens
by general contractor, subcontractor and sub-subcontractor that can be linked
from the Virginia Chapter have been modified to add lines necessary to
establish the existence of the claimant’s contractor’s license or certificate.
John S. Morris, III, Esquire (Contributing Author)
Beale, Davidson, Etherington & Morris, P.C.
Subscribe to:
Posts (Atom)
